Nuclear Installation Site Licence (NISL) application for the Thyspunt site

Closes 30 December 2026 (SAST) · Nuclear Installation Site Licence (NISL) application under the National Nuclear Regulator Act 47 of 1999, section 21(5)(b). Government Gazette reference to be confirmed.

Have your say

Site photo 1 for Nuclear Installation Site Licence (NISL) application for the Thyspunt site
The plain-language summary and the potential concerns on this page are prepared by ShapeSFB from the official documents. They are summaries, not official documents. The source documents are listed under Documents received below.

In short

  • Eskom has applied to the National Nuclear Regulator for a licence that would declare the Thyspunt site, between Oyster Bay and St Francis Bay, suitable for one or more new nuclear installations.
  • No reactor design, vendor or number of reactors has been chosen yet, so the application uses a range of possible designs with a maximum site capacity of about 33 000 MWth.
  • The reports conclude that the radiation dose to the public would be below the regulator's limits and that no external hazard rules the site out, but several studies are still outstanding.
  • Flooding from the sea, coastal erosion, tsunami risk and emergency planning for Oyster Bay and St Francis Bay are among the matters the reports say still need further work.
  • The documents provided do not contain a public comment deadline, a contact address for comments, or any environmental authorisation reference number.

Important note on the comment deadline

The public notice for this application states that written representations must reach the National Nuclear Regulator (NNR) within 90 days of publication in the Government Gazette. At the time of writing, the specific Government Gazette notice has not been located, so the exact closing date cannot yet be confirmed. ShapeSFB has asked the NNR to confirm the Gazette reference and the exact dates, and this page will be updated when they respond. If you intend to comment, please do so as early as possible.

What is being proposed?

This describes what Eskom has applied for, as set out in its own application documents.

Eskom Holdings SOC Limited has applied to the National Nuclear Regulator for a Nuclear Installation Site Licence (NISL) for the Thyspunt site on the Eastern Cape coast. A site licence is a decision about the site only: it says whether the land is suitable for a nuclear installation. It is not yet permission to build a specific power station. A separate Nuclear Installation Licence would be needed later once a reactor design is chosen (Public Information Document for the Proposed Thyspunt Site, p. 2, p. 20).

The site lies about 4 km east of Oyster Bay, about 12 km west of St Francis Bay and about 17.3 km south of Humansdorp (Public Information Document for the Proposed Thyspunt Site, p. 2, p. 48). It covers about 3 975.9 ha of Eskom owned land in 2024, possibly expanding to about 5 478 ha if more land is bought, partly for access roads (TSSR Chapter 3, Overview of Planned Activities, p. 7).

No reactor design, supplier or number of reactors has been chosen. Instead the application uses a "plant parameter envelope", which means the safety case is built around a range of possible pressurised water reactor designs rather than one specific plant (Public Information Document for the Proposed Thyspunt Site, p. 2, p. 23). Designs referred to as references include the AP1000, EPR, APR1400, HPR1000 and VVER type reactors (Public Information Document for the Proposed Thyspunt Site, p. 23, p. 25 to 26). At least two reactors are anticipated (TSSR Chapter 3, Overview of Planned Activities, p. 14).

The stated initial planned capacity is about 4 000 MWe (13 200 MWth), with an eventual maximum total site capacity of about 10 000 MWe (about 33 000 MWth) (TSSR Chapter 3, Overview of Planned Activities, p. 3, p. 11; Public Information Document for the Proposed Thyspunt Site, p. 4). Planned structures include reactor and auxiliary buildings, turbine halls, spent fuel storage, waste handling and storage, a desalination plant, a waste water treatment works, seawater intake and outfall structures, roads and 132 kV and 400 kV transmission lines (Public Information Document for the Proposed Thyspunt Site, p. 50 to 51).

Cooling would use a once through seawater system, with offshore tunnel intakes at minus 30 m mean sea level and an outfall channel at minus 5 m mean sea level (TSSR Section 5.9, Oceanography and Coastal Engineering, p. 5). The cooling water requirement is given as about 184 cubic metres per second for 4 000 MWe (Public Information Document for the Proposed Thyspunt Site, p. 120 to 121).

The indicative lifecycle is siting about 5 years, construction, operation for 60 years with possible extension, and decommissioning over about 20 years (TSSR Chapter 3, Overview of Planned Activities, p. 11; Public Information Document for the Proposed Thyspunt Site, p. 119). Low and intermediate level radioactive waste is proposed to be sent to the Vaalputs disposal site in the Northern Cape, transported via the N7, and spent fuel would be stored on site in the manner used at Koeberg (Public Information Document for the Proposed Thyspunt Site, p. 142, p. 144; TSSR Chapter 3, Overview of Planned Activities, p. 11).

Eskom states it will separately apply for environmental authorisation for the construction, operation and decommissioning of the station at Thyspunt (Public Information Document for the Proposed Thyspunt Site, p. 120). The documents supplied here are the nuclear siting safety documents, not that environmental application.

Key terms in this application

Plain-language explanations of technical terms used here. See the full glossary.

EIA (Environmental Impact Assessment)
The fuller assessment process for higher-impact activities. The more detailed assessment process (Scoping and Environmental Impact Reporting) used for larger or higher-impact activities. It usually runs in phases with more than one public comment period.

The site and what the specialists found

Everything in this section is a summary of what the applicant (Eskom) states in its own documents. These are the applicant's claims, put forward in support of its application, and are set out here so you can see what the application relies on. They have not been independently verified, and several of them are questioned in the concerns below, so they should not be taken as established fact.

The land and water around the site

The site is a greenfield coastal property made up of rocky headlands, sandy beaches and vegetated and unvegetated dunes (TSSR Chapter 3, Overview of Planned Activities, p. 7). Existing structures on it are a conservation workshop near the western boundary, three houses along the coast and two houses near the Langefonteinvlei wetland (TSSR Chapter 3, Overview of Planned Activities, p. 7).

There are no rivers on the site itself, but the reports record "ecologically important wetlands and springs", wetlands in the dune area and springs along the coast (Public Information Document for the Proposed Thyspunt Site, p. 48 to 49). Wetlands in the north eastern portion of the site are described as "the most significant hydrological features" (TSSR Section 5.10, Hydrology and Hydraulics, p. 3). Five vegetation types are listed: Algoa Dune Strandveld, Southern Cape Dune Fynbos, Tsitsikama Sandstone Fynbos, Cape Seashore Vegetation and Cape Lowland Freshwater Wetlands (TSSR Section 5.10, Hydrology and Hydraulics, p. 3, p. 13).

Part of the land within the 3 km emergency planning zone falls within the Garden Route Biosphere Reserve and a substantial portion within the Rebelsrus Private Nature Reserve (TSSR Chapter 11, Conclusions, p. 8). Marine Protected Areas in the wider region include the Tsitsikamma, Sardinia Bay and Gqeberha Corals MPAs, and the site falls within a Special Sea Area under the MARPOL convention for oil pollution protection (Public Information Document for the Proposed Thyspunt Site, p. 106).

Geology and earthquakes

Geological work has been carried out over more than 25 years (Public Information Document for the Proposed Thyspunt Site, p. 55). The site is underlain by Table Mountain Group sandstone with wind blown sand on top, up to about 65 m deep under inland dune peaks (Public Information Document for the Proposed Thyspunt Site, p. 56). No karst or cavern features were found, and the reports state there is "no evidence for capable tectonic deformation at the site location", meaning no faults that could move and rupture the ground (Public Information Document for the Proposed Thyspunt Site, p. 56, p. 58, p. 64). Liquefaction, where saturated loose soil behaves like a liquid during shaking, is said to exist in isolated areas and to be managed by founding the plant on bedrock (Public Information Document for the Proposed Thyspunt Site, p. 58). Soil slopes are said to need battering back to about 18 degrees and dewatering before stability can be assured (TSSR Chapter 11, Conclusions, p. 22). The earthquake hazard study used the SSHAC Level 3 process, an internationally recognised expert review method (Public Information Document for the Proposed Thyspunt Site, p. 3, p. 59).

The sea, flooding and erosion

The coastal study finds a rough wave climate with significant wave heights up to 14.7 m in 55 m of water offshore (TSSR Section 5.9, Oceanography and Coastal Engineering, p. 3). The best estimate maximum storm wave run up is 13.3 m above mean sea level in 2034, rising to 17.6 m by 2134, and 21.0 m under a high sea level rise scenario (TSSR Section 5.9, Oceanography and Coastal Engineering, p. 4). The main report states plainly that "flooding from the sea is therefore identified as a significant hazard that will need to be taken into account in the design" (Public Information Document for the Proposed Thyspunt Site, p. 87).

Coastal erosion is found to be more severe in Thysbaai than on the rocky coast to the west. By 2134 the nuclear installation corridor is exceeded by erosion lines for storms with exceedance frequency of 1E-02 per year and lower at a limited number of locations, and under the high sea level rise scenario along most of Thysbaai and the western half of the rocky coastline (TSSR Section 5.9, Oceanography and Coastal Engineering, p. 4). The specialist concludes "it will thus be necessary to move the position of the new NIs landward, or to design appropriate coastal protection such as revetments" (TSSR Section 5.9, Oceanography and Coastal Engineering, p. 4).

Modelling of the thermal plume found the worst case 99th percentile temperature rise at the intakes to be 0.51 degrees Celsius, below the 1.5 degree limit set in the plant parameter envelope (TSSR Section 5.9, Oceanography and Coastal Engineering, p. 5). Maintenance dredging will be required to prevent excessive sedimentation at the intakes, with less than 2 900 cubic metres per year of sand to be removed from landside intake basins (TSSR Section 5.9, Oceanography and Coastal Engineering, p. 6).

Radiation dose during normal operation

The dose assessment estimates the total annual dose to a representative member of the public at 171.52 microsieverts per year, made up of 164.85 from normal continuous discharges, 6.17 from minor occurrences and 0.50 from direct radiation (TSSR Chapter 7, PRIPE, p. 38). This is compared with the National Nuclear Regulator public dose limit of 1 000 microsieverts per year and the site dose constraint of 250 microsieverts per year (TSSR Chapter 7, PRIPE, p. 9 to 10, p. 49). The highest dose group was found to be adults in the east north east sector, at St Francis Bay (TSSR Chapter 7, PRIPE, p. 32). The report says the result is dominated by carbon 14 in the source term, conservatively assumed to be entirely in a form taken up by plants, whereas measured data from United States and German pressurised water reactors indicate that fraction averages only about 20 percent (TSSR Chapter 7, PRIPE, p. 44 to 45).

For plants and animals, the ERICA screening tool found all marine organisms below the default screening value of 10 microgray per hour, while terrestrial organism results exceeded the 10 microgray per hour default and were instead screened against the higher 40 microgray per hour value, against which they passed (TSSR Chapter 7, PRIPE, p. 42, p. 43).

Accident risk and emergency planning

A Level 3 Probabilistic Safety Assessment was carried out for a 6 unit EPR or 8 unit AP1000 configuration using the population within 50 km. The results are given as a percentage of the regulator's criteria: peak public risk 7.5 percent for the AP1000 and 2.12 percent for the EPR, and average site personnel risk 72.8 percent for the AP1000 and 32.97 percent for the EPR (TSSR Chapter 8, Emergency Planning, p. 20, p. 26). The report concludes these are well within the regulator's risk limits (TSSR Chapter 8, Emergency Planning, p. 26).

The proposed emergency planning zones are a precautionary action zone of 0 km, an urgent protective action zone and exclusion zone of 0.8 km, and a longer term zone of 40 km for food banning (TSSR Chapter 8, Emergency Planning, p. 16). The emergency planning chapter finds that the sheltering requirement is met for the EPR but not for the AP1000 at 0.8 km, where the projected dose is 22.803 millisieverts against a generic intervention level of 10 millisieverts, with the requirement met at 2 km (TSSR Chapter 8, Emergency Planning, p. 30 to 31, p. 44). In a postulated accident on 1 March, iodine 131 levels in leafy vegetables and milk are projected to exceed intervention levels for about one month (TSSR Chapter 8, Emergency Planning, p. 38).

People, farming and land use

The population within 50 km was about 119 615 people in 2022, projected to about 245 034 permanent residents by 2130 (TSSR Section 5.4, Demography, p. 46, p. 86). Oyster Bay is the only settlement within 6.5 km, with about 818 people in 2022 and a projected 1 145 by 2130 (TSSR Section 5.4, Demography, p. 52, p. 4). St Francis Bay is the largest settlement within 16 km, projected at 12 078 people by 2130 (TSSR Section 5.4, Demography, p. 4). A tourism survey estimated a maximum of 6 287 visitors per day within 80 km in peak season, with December the busiest month (TSSR Section 5.4, Demography, p. 66).

The Kouga Spatial Development Framework of 2021 already contains a Thyspunt policy: urban expansion of Oyster Bay and Umzamowethu within the 0 to 5 km zone should not be permitted, institutional uses such as prisons, old age homes and hospitals should not be developed within 16 km because of evacuation difficulty, no new food processing plants within 16 km, and agricultural activities to be monitored within 16 km (TSSR Section 5.4, Demography, p. 144 to 146; Public Information Document for the Proposed Thyspunt Site, p. 109 to 110). The Humansdorp area is described as the largest milk producer in South Africa, with dairy farming dominant within 16 km (TSSR Chapter 8, Emergency Planning, p. 37, p. 53).

Water supply in the area is already under pressure. The reports state that "overall, the AWSS is in deficit as a result of over-allocation" and that Kouga Local Municipality "has effectively reached the limit of its allocations" from the Algoa Water Supply System (Public Information Document for the Proposed Thyspunt Site, p. 104).

Overall conclusions in the reports

The Site Safety Report concludes that "no external hazards have been identified that would preclude the siting of the proposed nuclear installation on the Thyspunt site" and that "clear evidence has been provided to support the suitability of the site" (TSSR Chapter 11, Conclusions, p. 23, p. 26). It also records that several matters remain to be resolved in later licensing stages.

Potential concerns and unresolved questions

The following matters are drawn from the application documents themselves. They include points the reports flag as unresolved or deferred, places where the application relies on assumptions or on data that may not reflect current local conditions, figures that appear inconsistent with what is known locally, and material that is redacted or not fully explained. They are set out as questions and requests for verification, so that readers can decide which, if any, they wish to raise.

1. The seismic hazard assessment is central to the site decision but published only in redacted form

The suitability of the site depends heavily on its seismic hazard. The application assesses this through a probabilistic seismic hazard analysis and concludes that there are no capable faults at the site, assigning the regional offshore faults a low, 20 percent, probability of being able to generate earthquakes (TSSR Section 5.14; TSSR Section 5.13). The seismic hazard section is, however, published only as a redacted version, so a number of the specific inputs and values behind these conclusions are withheld from the public, which limits independent scrutiny of a safety-critical part of the case.

You may wish to ask the National Nuclear Regulator to confirm that the seismic hazard basis is adequate and appropriately conservative, and to make the full seismic hazard analysis available to reviewers, or to explain how the redacted inputs were independently verified.

Main reference to cite: TSSR Section 5.14 Seismic Hazard; TSSR Section 5.13 Geology

2. No site-specific tsunami hazard analysis is presented in the Site Safety Report

The oceanography and coastal section states that no tsunami results are presented in this Site Safety Report, and recommends that an updated Tsunami Hazard Analysis be undertaken for Thyspunt and the report then updated once the results are available. In the meantime the flooding assessment is based on storm wave run-up only, and an interim tsunami run-up figure is drawn from the separate Duynefontyn site study rather than from a Thyspunt-specific analysis (TSSR Section 5.9). The same section identifies a tsunami combined with sea-level rise, high tides and storm surge as a flooding mechanism, but this combination is not quantified.

You may wish to ask the National Nuclear Regulator to require a completed, site-specific tsunami hazard analysis for Thyspunt, including the combination of a tsunami with storm surge and sea-level rise, before the site safety case is relied on.

Main reference to cite: TSSR Section 5.9 Oceanography and Coastal Engineering

3. The urgent protective action zone is much smaller than the regulator's own benchmark

Eskom's own Final Scoping Report records the National Nuclear Regulator's established emergency planning criteria, under which the urgent protective action zone is in the range of 5 km to 16 km. The application for this site instead sets the urgent protective action zone, and the exclusion zone, at 0.8 km, and reduces the longer-term food-control zone from the generic 80 km to 40 km (TSSR Chapter 8). These reductions rest on deterministic consequence analysis carried out for reactor designs that have not yet been chosen. Control of land use within the zones depends on the municipal Spatial Development Framework, which is itself subject to periodic review.

You may wish to ask the National Nuclear Regulator to confirm how an urgent protective action zone of 0.8 km is justified against its own benchmark of 5 km to 16 km, how it is kept robust to the final reactor choice, and how control of land use within the zones will be assured.

Main reference to cite: TSSR Chapter 8 Emergency Planning; Final Scoping Report, citing National Nuclear Regulator criteria (2005 and 2006); TSSR Section 5.4 Demography

4. No completed evacuation model, and limited road access

As recorded in Eskom's Final Scoping Report, the National Nuclear Regulator's criteria require that evacuation be demonstrated by a traffic evacuation model accepted by the regulator, within set times. No such model has been completed: the traffic study defers the evacuation time estimate to a later stage (Traffic Scoping Report, Appendix G20). Road access to the area is limited, being served by the R330 provincial road, which has a single lane in each direction and no shoulders, with the coastal settlements of Oyster Bay, St Francis Bay and Cape St Francis reached off it (TSSR Section 5.7; Traffic Scoping Report, Appendix G20).

You may wish to ask the National Nuclear Regulator to require a completed and accepted traffic evacuation model, tested against peak-season conditions and the limited road access, before the site is licensed.

Main reference to cite: Final Scoping Report, citing National Nuclear Regulator criteria; Traffic Scoping Report (Appendix G20); TSSR Section 5.7 Nearby Transportation; TSSR Chapter 8 Emergency Planning

5. The sheltering dose criterion is not met at the proposed exclusion distance for one reference design

For one of the candidate reactor designs, the AP1000, the application's own analysis shows the projected sheltering dose at the proposed 0.8 km boundary is 22.8 millisieverts, against a generic intervention level of 10 millisieverts, and the criterion is met only at 2 km (TSSR Chapter 8, Table 8.8). For the other reference design, the EPR, the criterion is met at 0.8 km.

You may wish to ask the National Nuclear Regulator to clarify how an exclusion and urgent-protective-action distance of 0.8 km is justified when one candidate design meets the sheltering criterion only at 2 km, and to confirm that the final design will meet it at the licensed boundary.

Main reference to cite: TSSR Chapter 8 Emergency Planning, Table 8.8

6. Whether emergency planning and dose use the real peak-season and construction populations

The demography section projects a maximum of 8 743 tourists within the 50 km radius on any one day in the December peak (TSSR Section 5.4). Yet the same section records, for example, a single annual festival about 12.5 km from the site drawing up to 15 000 visitors per day, and Eskom's Final Scoping Report records a construction workforce of around 10 000 people. Emergency planning and the public dose assessment both depend on the population actually present, and the headline peak figure appears low against the site's own recorded seasonal and event populations.

You may wish to ask the National Nuclear Regulator to confirm that emergency planning and the dose assessment are tested against the real peak-season, event and construction populations, rather than an off-peak or accommodation-only figure.

Main reference to cite: TSSR Section 5.4 Demography; TSSR Chapter 7 PRIPE; Final Scoping Report (construction workforce)

7. No reactor technology has been chosen, and smaller modular reactors are not assessed

No reactor design, supplier or number of reactors has been selected. The safety case is built on a plant parameter envelope covering a range of large Generation III pressurised water reactor designs, for a site with an eventual capacity of up to 10 000 MWe (signed application; PID; TSSR Chapter 3). Eskom's radiological report records that Eskom may also consider Generation IV small modular reactors, including gas-cooled designs, but that the site safety reports submitted to the regulator do not include a Generation IV type reactor, and that for such reactors the dose criteria are only expected to be met.

You may wish to ask the National Nuclear Regulator to clarify which site-suitability conclusions are provisional on the final design, and how site suitability would be re-established if a Generation IV or small modular reactor is later selected.

Main reference to cite: Signed NISL application; PID; TSSR Chapter 3 Overview of Planned Activities; Radiological Impact Report (Appendix G21)

8. Flooding from the sea and coastal erosion reaching the installation area

The coastal study finds the best-estimate maximum storm wave run-up rising from 13.3 m above mean sea level in 2034 to 17.6 m in 2134, and 21.0 m under a high sea-level-rise scenario, and that the flood and erosion lines extend into the Nuclear Installation Corridor by 2134, along most of Thysbaai and the western rocky coast under high sea-level rise (TSSR Section 5.9). The study states it will be necessary to move the installations landward or to design coastal protection such as revetments and wave walls, and that the detailed protection design is left to a later stage.

You may wish to ask the National Nuclear Regulator to require the final sea-flood and erosion protection design, and verification that safety-critical structures stay protected over the full life of the installation including under high sea-level rise, before the site is confirmed or before construction.

Main reference to cite: TSSR Section 5.9 Oceanography and Coastal Engineering; TSSR Chapter 11 Conclusions

9. Deep excavation, continuous dewatering and foundation measures still to be finalised

The geotechnical characterisation describes the single most significant issue as slope stability of the excavation, which reaches about 40 m to bedrock, needs to be battered back to about 18 degrees, and requires robust, uninterrupted dewatering of the underlying aquifer, with excavations potentially open for years (TSSR Section 5.15). It also records that the required bearing capacity can only be achieved with ground improvement, that liquefaction potential exists in isolated saturated zones, and that the liquefaction assessment is to be revised. These measures are described at a conceptual level.

You may wish to ask the National Nuclear Regulator to require that the final foundation, slope-stability, dewatering and liquefaction designs be completed and independently verified before construction.

Main reference to cite: TSSR Section 5.15 Geotechnical Characterisation; TSSR Section 5.11 Geohydrology

10. Protection of the local groundwater and drinking-water supply

The site overlies the Algoa Aquifer, which the application records as supplying the towns of Oyster Bay, Humansdorp and St Francis Bay with water (TSSR Section 5.11). The study models a liquid leak from the installation as confined to the footprint, with monitoring and remediation to follow, while also noting that the groundwater investigation and monitoring period has been relatively short.

You may wish to ask the National Nuclear Regulator to confirm that the containment, detection and remediation measures are adequate to protect the local groundwater and drinking-water supply, given the short monitoring baseline.

Main reference to cite: TSSR Section 5.11 Geohydrology

11. Spent fuel and high-level waste would be stored on site with no final disposal route

Spent nuclear fuel would be held on site, first in the spent fuel pool and then in interim storage, until a deep geological repository is available. Eskom's radioactive waste report records that there is no operational deep geological repository for high-level waste, that the disposal programme may take several decades, and that endpoint planning for high-level waste has historically not received sufficient prominence (Radioactive Waste Management and Transport report, Appendix G22).

You may wish to ask the National Nuclear Regulator to confirm the safety case and expected duration for on-site spent-fuel and interim waste storage, and how the absence of a final high-level-waste disposal route is addressed in the site safety case.

Main reference to cite: Radioactive Waste Management and Transport report (Appendix G22); TSSR Chapter 3 Overview of Planned Activities

12. The public radiation dose rests on conservative assumptions for a reactor not yet chosen

The assessment estimates the annual dose to a representative member of the public at about 0.171 millisieverts per year, below the site dose constraint of 0.250 and the public dose limit of 1.0 millisievert per year (TSSR Chapter 7; Radiological Impact Report, Appendix G21). The figure rests on conservative, enveloping discharge assumptions for a range of Generation III designs and the full-site capacity, and the radiological report states a reassessment with more realistic, design-specific assumptions would be done at the construction-licence stage. The assessment finds both candidate sites meet the dose constraint.

You may wish to ask the National Nuclear Regulator to require that the public dose assessment be re-confirmed with site-specific and design-specific source terms once a reactor design is chosen, and that operational monitoring verify the representative-person dose.

Main reference to cite: TSSR Chapter 7 PRIPE; Radiological Impact Report (Appendix G21)

13. Much of the safety documentation is in redacted public versions

Several of the application sections are published as redacted versions, including the seismic hazard, demography, meteorology, oceanography, transportation, potential radiological impact and emergency planning sections. While most of the text is readable, specific inputs and values are withheld, which limits independent public scrutiny of parts of the safety case.

You may wish to ask the National Nuclear Regulator whether complete, unredacted versions are available to reviewers, and how the withheld inputs were independently verified.

Main reference to cite: TSSR Sections 5.4, 5.7, 5.8, 5.9 and 5.14 and Chapters 7 and 8 (redacted public versions)

14. Many safety matters are deferred to later licensing stages

The Site Safety Report concludes that no external hazard would preclude siting, while also stating that its conclusions rest on assumptions for the purpose of the initial licensing stage, and recording that a number of matters remain to be completed at later stages. These include the final flood and erosion protection design, the site-specific tsunami hazard analysis, the final geotechnical and liquefaction designs, the design-specific dose assessment, the security plan and defensive strategy, and baseline environmental radioactivity monitoring before commissioning (TSSR Chapter 11).

You may wish to ask the National Nuclear Regulator for a consolidated list of the studies and verifications still outstanding, the stage at which each will be completed, and whether each will be made available for public comment.

Main reference to cite: TSSR Chapter 11 Conclusions; TSSR Section 5.9; TSSR Section 5.15; TSSR Chapter 7; TSSR Chapter 8

15. Combinations of events, and beyond-design-basis events, are deferred or not yet quantified

Serious nuclear accidents often arise from a combination of events happening together, as at Fukushima, where an earthquake, a tsunami and a loss of power occurred at once. The application does set out an approach to combinations of external events and assesses severe, beyond-design-basis accidents (TSSR Chapter 6, Combination of External Events; TSSR Chapter 8, severe accident assessment). However, for several hazards the combined assessment is deferred to later studies that are both site-specific and design-specific, for a reactor that has not yet been chosen, and the specific combination of a tsunami with a storm surge and sea-level rise is identified but not quantified, because the site-specific tsunami hazard analysis is still outstanding (TSSR Section 5.9).

You may wish to ask the National Nuclear Regulator to confirm that combinations of external events and beyond-design-basis events, including a seismically generated tsunami coincident with a storm surge and with a loss of off-site power, are adequately assessed for this site and reactor choice before the site safety case is relied on.

Main reference to cite: TSSR Chapter 6 Evaluation of External Events (Section 6.12 Combination of External Events); TSSR Section 5.9 Oceanography and Coastal Engineering; TSSR Chapter 8 Emergency Planning

How to make your submission

Anyone who may be affected can make a written representation to the National Nuclear Regulator (NNR) on the nuclear and radiological safety of this application. You do not have to be an expert, and you do not have to prove that the whole site is unsafe. A clear, specific point about something you know first-hand is valuable to the regulator.

Where to send it: by email to NISLcomments@nnr.co.za, marked for the attention of the NNR Programme Manager: Nuclear Power Plants. Postal and hand-delivery addresses are in the public notice. Send it within the comment period. The exact closing date is not yet confirmed (see the note at the top of this page), so please comment as early as you can.

What makes a strong submission: your own words, your own circumstances, and specific facts. A short, personal, factual submission carries more weight than a signature on a petition.

A simple structure you can follow:

  1. Where I live or spend time.
  2. My specific concern.
  3. The local facts or personal circumstances that support it.
  4. What I want the NNR to investigate, explain or require.

Issues you may know about first-hand, which the safety assessment should reflect:

  • Your ability to evacuate: whether you have a vehicle, limited mobility, young children or dependants, or would need help to leave.
  • Road conditions and congestion: specific bottlenecks, holiday traffic, flooding or closures you have seen, with locations and dates if you can.
  • Receiving and understanding warnings: mobile coverage where you are, language needs, or visitors unfamiliar with local routes.
  • Where people actually spend time: homes, schools, workplaces, beaches and fishing areas that should be reflected in the population and exposure assessments.
  • Food, water and livelihoods: locally caught seafood, home-grown produce or borehole water that may be relevant to radiological exposure.
  • Questions the documents do not answer clearly: what the assessed risks mean for your household, and what protective actions might be required.

You are welcome to use any of the concerns on this page as a starting point, but put them in your own words and add your own knowledge of the area.

Have your say

19 submissions have been made so far.

Your submission will be delivered to: NNR Programme Manager: Nuclear Power Plants (National Nuclear Regulator).

You can comment now without registering separately. Submitting your comment also records you as an Interested and Affected Party, so you are notified of the outcome.

It takes about two minutes. Pick your position, then say why in your own words. Not sure what to write? Tick a concern below and a starting point appears.

As a guide, a strong comment usually includes, in your own words
  1. Who you are: resident, business owner, both, visitor, or a concerned member of the public.
  2. The local facts or personal circumstances behind your concern.
  3. What you want the authority to investigate, explain or require.

You choose which concerns to comment on in the next section, then add your facts and your ask under each one.

One or two sentences on where you live or work and why this matters to you. This opens your submission.

A few sentences is enough. Comments in your own words carry more weight than copied text.

Pick the concerns you share, then add your reasons.

Tick any concern below and a box opens. In it, add your local facts and what you want the authority to do, in your own words. That carries the most weight.

0 characters (at least 40)

Anyone may comment. You do not have to live next to the development to have a say. We ask where you are from so the authority can see where comments come from. It does not limit your right to comment.

Know someone this affects? Share it so they can take part too.